Newsletter No. 2 May 8, 2014 When we last spoke two weeks ago, this is was what the house looked like. If you missed our last newsletter, you can r

         
CPRnewsletterheader

Newsletter No. 2

May 8, 2014

SDC10229

When we last spoke two weeks ago, this is was what the house looked like.

If you missed our last newsletter, you can read it here.

***
 DSC3365

Thanks to the team at TMD Windows and Doors, windows were installed this week!

Doors came from Tibbetts Lumber and were installed by Vince Mantegna of Crown & Trim by Design. Thank you for your patience, Vince!!

calendar2
Drywall begins on Monday, May 5th
Shopping for cabinets on Monday, May 5th
Garage door to be installed Monday, May 12th (or sooner)
Anticipate painting to begin by Wednesday, May 14th
Anticipate installing cabinets Saturday, May 17th

checkmark

Things we still need:

1. Kitchen cabinets
2. Painter
3. Landscaper | Irrigation | Sod
4. Concrete | Driveway | Sidewalk
5. Grading Contractor
6. Cleaner

***